During the course of next week, Transport for Buckinghamshire will be carrying out work at the following locations. The dates shown are subject to change at short notice, especially with the surface dressing programme which is weather dependent.
No weekend or Bank Holiday working unless otherwise specified.
Conventional Surfacing Programme
North Orbital Service Road, Denham (29/08/2017 to 30/08/2017)
Daytime kerbing works using localised traffic management between 07:30 and 17:00hrs
Surface Dressing Programme
The Vale, Hawridge – Pound Lane to Greenway (29/08/2017 to 01/09/2017) Daytime surface dressing preparatory works using a daytime road closure between 09:30 to 15:30hrs
Missenden Road, Butlers Cross – Lodge Hill and Chequers bends (29/08/2017) Daytime works using a road closure between 09:30 to 15:30hrs
Rignall Road, Great Missenden – 30mph limit to Aylesbury Road (29/08/2017 to 30/08/2017) Daytime works using a road closure between 09:30 to 15:30hrs
Poles Hill & Darvell Drive, Chesham – Whole Length of Road (30/08/2017 to 31/08/2017)Daytime works using a road closure between 07:00 to 19:00hrs
Iron Work adjustments
Swallow Street, Iver – Various locations along whole length (29/08/2017) Daytime ironwork adjustments using localised traffic management between 07:00 and 19:00hrs.
Church Road, Farnham Royal – Various locations along whole length (30/08/2017) Daytime ironwork adjustments using localised traffic management between 07:00 and 19:00hrs.
Wexham Street, Wexham – Various locations along whole length (30/08/2017) Daytime ironwork adjustments using localised traffic management between 07:00 and 19:00hrs.
Berry Hill, Taplow – Various locations along whole length (30/08/2017) Daytime ironwork adjustments using localised traffic management between 07:00 and 19:00hrs.
Heath End Road, Flackwell Heath – Various locations along whole length (31/08/2017) Daytime ironwork adjustments using multi way traffic signals between 07:00 and 19:00hrs.
Marlow Road, Lane End – Various locations along whole length (31/08/2017) Daytime ironwork adjustments using localised traffic management between 07:00 and 19:00hrs.
Lower Road, Great Brickhill – Various locations along whole length (01/09/2017) Daytime ironwork adjustments using two man stop and go boards between 07:00 and 19:00hrs.
Other
Aylesbury Road, Great Kimble – Bridge Street to Askett roundabout (29/08/2017) Daytime road stud installation using stop and go boards between 09:30 and 15:30hrs.
Gravel Hill, Chalfont St Peter – Deanacre Close to Joiners Lane roundabout (30/08/2017) Daytime road stud installation using stop and go boards between 09:30 and 15:30hrs.